Paved Roads & Submitted for Plat Approval

In April 2025, we installed gutters and laid the initial base layer. In May, curbs were backfilled and the final base layer completed. In June, roads were paved, property dress-ups finalized, and the plat submitted. Next steps are to receive approval and pursue an LOI.

In April 2025, we installed gutters and laid the initial base layer.

In May, curbs were backfilled and the final base layer completed.

In June, roads were paved, property dress-ups finalized, and the plat submitted.

Next steps are to receive approval and pursue an LOI.

1750968851926

More Projects Update

We previously completed horizontal development on the 41-lot short phase within Phase 2, and the plat has been submitted and approved. In the remaining section of the property, water and electrical utilities are in place, with base and curb work next.
Nine units in Phase 1 are finished, with Certificates of Occupancy in hand and ready for lease-up. Five more units on Lots 58 through 62 are being brought to CO, and the building permit application for the next 18 lots has been submitted ahead of vertical construction.