Addressed Comments on Permit

We received the Land Disturbance Permit and Civil Plan approval for Haselton Phase 3: The Cliffs at Lake Lanier. For Phase 2, we addressed comments and resubmitted the permit. Once all three phases are permitted, we will finalize the project sale.

We have received a Land Disturbance Permit (LDP) and approval for the Civil Plans for Haselton Phase 3: The Cliffs at Lake Lanier.

We’ve already addressed the comments for Phase 2 and have resubmitted the permit for approval.

Once we obtain the permits for all three phases, we’ll finalize the sale of the project.

1745852038385

More Projects Update

We previously completed horizontal development on the 41-lot short phase within Phase 2, and the plat has been submitted and approved. In the remaining section of the property, water and electrical utilities are in place, with base and curb work next.
Nine units in Phase 1 are finished, with Certificates of Occupancy in hand and ready for lease-up. Five more units on Lots 58 through 62 are being brought to CO, and the building permit application for the next 18 lots has been submitted ahead of vertical construction.
Two more properties recently went live, one outside Clearwater, Florida and one lakefront in the Poconos, both five-bedroom, eight-bed homes with full amenity packages. Since acquiring 142 rentals in December 2024, the portfolio has grown to 153 units.