Fully Prepared to Break Ground

In Q1 2025, we completed due diligence and officially added this project to the Fund. We’ve secured the site development permit and finalized architectural plans, and are preparing to break ground soon. Estimated delivery: end of Q2 2026.

In Q1 2025, we completed our due diligence and officially added this project to the Arabella Real Estate Fund.

Last quarter, we successfully obtained a site development permit and finalized the architectural plans.

We are now fully prepared to break ground and begin horizontal development in the next few weeks.

This project will have a 12-month development period with an estimated delivery at the end of Q2 2026.

1752169093355

More Projects Update

We previously completed horizontal development on the 41-lot short phase within Phase 2, and the plat has been submitted and approved. In the remaining section of the property, water and electrical utilities are in place, with base and curb work next.
Nine units in Phase 1 are finished, with Certificates of Occupancy in hand and ready for lease-up. Five more units on Lots 58 through 62 are being brought to CO, and the building permit application for the next 18 lots has been submitted ahead of vertical construction.
Two more properties recently went live, one outside Clearwater, Florida and one lakefront in the Poconos, both five-bedroom, eight-bed homes with full amenity packages. Since acquiring 142 rentals in December 2024, the portfolio has grown to 153 units.