April 2025 – Finalizing budgets for Emma Phases 1 and 2, working on zoning for Phase 3, and developing the commercial business plan.
May 2025 – Confirmed pricing for Phase 1, held a pre-construction meeting for Phase 2, addressed zoning comments for Phase 3, and progressed on the commercial plan.
June 2025 – Finalizing bank terms for Phase 1, began construction on Phase 2, awaiting zoning approval for Phase 3, and advancing the commercial plan.
Next Steps – Begin construction on Phase 1, complete sewer and stormwater installation for Phase 2, submit for Phase 3 permitting, and finalize the commercial business plan.